14L Status Compaction in Progress,
Contractor waiting regarding termite proofing agent approval.
Make AGENDA approved for termite proofing – 03rd April, 2017
Termite Proofing Work Started 04th April, 2017.
Lean Concrete Completed 04th April, 2017.
Layout, Steel Cutting & Curing In Progress.
Removal of Material from 13L In Progress.
Footing Concrete Pouring 10th April, 2017 Open 03-04-17
13L Status Floor Removal Completed.
Plaster Removal Completed.
Removal of Debris in Progress.
Slab Cutting Will be started on 4th April, 2017.
Chipping below slab started. 04th April, 2017
Column Digging Started 05th April 2017.
Girder Installation & Cordon off Work Start By 07th April, 2017.
Structure Engineer Immediate Visit Required, IAA to coordinate/email to Mr. Amjad Niazi 10th April, 2017. Open 10-04-17 10-04-17